The requested transfer of $231,463 from C37919 Engineering Building Renovations to C37935 Mechanical Infrastructure Replacement will fully fund the first phase of this project and begin planning for the next phase. The Engineering Building Renovation was recently completed and the remaining appropriation in C37919 will not be needed for that project.
The Mechanical Infrastructure Replacement Project is anticipated to be a three to four biennia project to upgrade the campus mechanical infrastructure. Existing infrastructure is original to the 1960's and 70's campus construction and is beyond its useful life. Modern mechanical systems last longer, are more energy efficient, and provide increased comfort to students, faculty, and staff.
A Request for Qualifications was posted in the Ohio Register on August 26, 2025. Four (4) firms submitted Statements of Qualifications on September 23, 2025. Two (2) firms were shortlisted to submit proposals in response to the Request for Proposals issued on October 14, 2025. Through the interview and selection process, Brewer Garrett Company was selected based on their best value score and quality of the team to perform the required services.
Brewer-Garrett offered the best response for addressing Guaranteed Maximum Price 1 and developing a fee structure for implementation of the project. Per Section 357.45 of Sub HB 2, Lakeland Community College is contracting with Brewer Garrett up to $925,000 for preconstruction services for Guaranteed Maximum Pricing packages 1 and 2 and construction services for GMP 1.